Construction at Disney’s Hollywood Studios is moving forward in the area that used to be Muppets Courtyard. New overhead photos show how crews are reworking existing buildings and rebuilding the ground between them for Monstropolis. This article looks at what the images show, how the work connects to the planned Monsters, Inc. door coaster, and what Disney has said about timing.
From Muppets Courtyard to Monstropolis

Monstropolis is replacing Muppets Courtyard, and the project involves more than a new coat of paint. Crews are transforming existing structures while rebuilding the courtyard that links them. Overhead views from the photographer bioreconstruct offer a useful way to follow that progress, because they show how the buildings, walkways, and future ride areas relate to one another.
Disney has said the land will open in phases beginning in 2027. The door coaster, which will be Disney’s first vertical lift coaster and first suspended coaster, will debut later. No opening timeframe has been announced for that attraction.
Work Near The Glob Theater and Harryhausen’s Restaurant
One straight-down photo focuses on the area near the exit of The Glob Theater and Harryhausen’s Restaurant. Guests will likely walk through this space to reach the Monsters, Inc. factory and its suspended door coaster, which makes it one of the key connection points in the land.

Much of the ground here is still exposed dirt. The photo shows excavated trenches, concrete walls, and stacks of construction materials sitting between the buildings. The low walls outline several angular sections, and equipment and work vehicles are parked around the edges. Scaffolding also remains along the neighboring façades.
From this vantage point, it is easier to see how the existing courtyard will tie into the coaster expansion beyond it.
The Octagonal Fountain and Wider Courtyard Progress
Two wider aerial views place the work in a broader context. Both include the octagonal fountain near The Glob Theater. Its concrete basin is visible inside surrounding wooden forms, with a vertical element rising from the center. Earlier reports covered entrance brickwork and construction around the fountain. These new angles show it surrounded by large areas of ground that have not yet been paved.

Near the Land Entrance
Closer to the entrance, a circular inset is visible in a section of pavement between the entrance columns. The photos do not make clear what the feature will become, so it is best to treat it as a detail to watch in future updates.
Deeper in the Courtyard
Farther inside, long concrete walls form angular outlines beside the future guest route. Exposed reinforcing grids cover sections that are waiting for more concrete. Crews are also working around an excavation beside the theater’s entrance, and construction vehicles, material stacks, and scaffolding are spread across the courtyard.

Aerial Observations at a Glance
The table below summarizes what the overhead photos show in each area of the courtyard.
| Area | What the Aerials Show |
|---|---|
| Near The Glob Theater and Harryhausen’s exit | Exposed dirt, trenches, concrete walls, and construction materials along the likely guest route to the factory and coaster |
| Octagonal fountain | Concrete basin inside wooden forms with a vertical element in the center |
| Land entrance | A circular inset in pavement between the entrance columns |
| Interior courtyard | Long concrete walls with angular outlines and exposed reinforcing grids awaiting concrete |
| Beside the theater entrance | Active excavation with surrounding vehicles and material stacks |
| Building façades | Scaffolding still in place around several structures |
Scaffolding Starts to Come Down
Although scaffolding still surrounds several buildings in the aerial shots, the most recent ground-level update documented a change in the look of the façades. More horns, spikes, and tooth-like trim are becoming visible as the scaffolding is removed. That suggests exterior theming work is progressing on the buildings even while the courtyard between them is still being rebuilt.
The Door Coaster and the Opening Timeline
The route being prepared in the courtyard leads toward the Monsters, Inc. factory and the suspended door coaster. Disney has released artist concept art showing riders seated in suspended vehicles moving past rows of colorful doors, with Sulley, Mike, and Boo appearing on a door in the foreground. The artwork is a concept only, so final details may differ.

The table below outlines what has been confirmed so far.
| Item | Current Status |
|---|---|
| Monstropolis land | Opening in phases beginning in 2027 |
| Monsters, Inc. door coaster | Under construction, opening later with no announced timeframe |
| Coaster type | Disney’s first vertical lift and first suspended coaster |
| Replaces | Muppets Courtyard |
What to Watch for in Future Updates
As construction continues, several details in the courtyard should become clearer over the coming months.
- Paving and finishing around the octagonal fountain
- The purpose of the circular inset near the entrance columns
- Concrete pours over the exposed reinforcing grids
- More scaffolding removal and the horns, spikes, and trim it reveals
- The finished guest route between The Glob Theater, Harryhausen’s, and the factory
- Announcements about the door coaster opening timeframe
Final Thoughts
The latest aerial photos show a courtyard in the middle of heavy groundwork, with trenches, concrete walls, and a fountain basin all taking form around the buildings that will make up Monstropolis. The land is scheduled to open in phases beginning in 2027, with the door coaster arriving afterward, so progress photos like these remain a useful way to follow how the pieces will fit together.