Construction in the northwest corner of Magic Kingdom has reached an early but meaningful stage. New aerial photos of the future Villains Land show expanded staging, fresh grading, and the first signs of where attraction buildings will eventually stand. The work is still focused on dirt and utilities, but it offers a clear sense of how the project is progressing. Here is a closer look at what the latest images reveal.
What the New Aerial Photos Show

The newest overhead views capture the sprawling Villains Land site spread across the former Rivers of America basin. Big Thunder Mountain Railroad still marks the southern edge of the work, while the area to the north and west has been opened up for the expansion.

The clearest theme in these photos is staging. Crews have set up large laydown areas filled with pipe, precast manholes, and other construction materials across much of the site. This kind of preparation is not flashy, but it lays the groundwork for the attractions, dining, and shopping that will follow.
Why the Lighter Dirt Matters

One detail worth watching is the lighter-colored dirt visible throughout the site. These pale, compacted areas point to early land grading, the leveling and prep work that creates the pads where show buildings will eventually sit.
The grading lines up reasonably well with the layout Disney filed in a January 2026 permit. That filing listed several structures, including a building of roughly 83,000 square feet, along with others at about 55,000, 16,000, and 8,500 square feet, plus a smaller 5,800 square foot building near the Haunted Mansion. The graded areas falling within that same footprint suggest the early pad work is following the permitted plan.
Underground Utility and Stormwater Work

The other major story in these images is the infrastructure going into the ground. Crews are digging trenches and placing stormwater pipes and conduit across the site, with precast manholes staged nearby and ready for installation.
This underground work has to be completed before the building pads can be finished and built upon. The color-coded pipe runs and staged manholes indicate that the stormwater and utility backbone for the expansion is actively being installed, a necessary step that supports everything built on top of it later.
How the Site Lines Up With the Permitted Layout

The January 16 permit gave fans concrete building footprints to measure against, which makes it easier to interpret the current activity. Beyond the building sizes, that filing also pointed to more than 9,000 additional guests of daily capacity once the expansion is complete.
The grading and utility work shown in the aerials sits within that same basin footprint. The northeast show building behind the Haunted Mansion stands out as one of the more recognizable graded areas. It is widely believed to be an immersive dark ride, though Disney has not confirmed the theme. As more pads firm up, matching graded sections to specific permitted buildings should become more straightforward.
The Project Timeline So Far

Villains Land has moved through several documented steps over the past year. A look at the filings and earlier reporting helps put the current work in context.
- In October 2025, Disney filed a permit covering drain lines across roughly 33 acres tied to both the Cars and Villains projects.
- A January 2026 permit revealed the building layouts for Villains Land and the Cars-themed Piston Peak National Park.
- Analysis of those permits indicated the infrastructure work was targeted for completion by 2028.
- Aerial photos in March 2026 showed early infrastructure work and land grading getting underway across the site.
What Comes Next

The infrastructure phase remains targeted for completion by 2028. Beyond that, Piston Peak National Park is expected to open around 2029, with Villains Land projected for 2030 or later. Disney has not confirmed firm opening dates for either project, so these timeframes should be treated as estimates rather than official targets.
For now, the focus stays on earthwork and utilities, with show building pads only beginning to take form. The next stretch of progress will come as those pads firm up and vertical construction eventually begins.
Conclusion
The latest aerials show Villains Land moving steadily through its early phase, with staging, grading, and utility work all advancing in the former Rivers of America basin. The lighter dirt marking future building pads and the underground pipe installation both signal that the groundwork for this expansion is well underway. With infrastructure aimed at a 2028 finish and the land itself still years out, there is plenty left to track as the project continues to develop.